"It's interesting that our first winner was the inventor of the computer, and this year's winner (George Danzig) came up with one of the first business applications for the computer (Linear Programming)."Jeffrey Coors, President, Adolph Coors Company on the occasion of the presentation of the 1989 Coors American Ingenuity Award
6.1: Problem Formulation
Introduction
George Danzig is the father of the most
powerful of all quantitative methods: linear programming, the subject
of this and the final two modules of the course. He came up with his
idea of developing a mathematical model to mechanize the military's
planning process during World War II. After the war, once linear
programming reached the private sector, it was quickly recognized as
the most effective decision-support tool the world has ever seen.
Linear programming's rise to prominence began in the oil companies in
the 1950's. "We used linear programming to schedule our tanker
fleets, design port facilities, blend gasoline, create financial
models, you name it," says Bill Drew, former manager of research for
Exxon. Quickly linear programming became commonly used to:
- solve environmental problems
- make decisions to improve the economy of small countries
- help investors make the best portfolio decisions
- schedule worldwide air travel
- develop global business strategies
- improve government functions and ideas
- schedule automobile assembly line production
My first application of linear programming came
about at the Pentagon when I joined a joint service task force to
create a unified transportation command. We envisioned that a unified
command would have the command and control needed to enable the use
of linear programming to develop optimum airlift deployment schedules
to quickly move troops and their equipment into hot spots around the
world. Although I retired before it's the first real test (Desert
Storm), I was pleased to read the after action reports of the success
of the deployment model. Models such as the one used by the unified
transportation command are common place in distribution systems in
the private sector.
All linear programming problems have the following operational
characteristics:
- an objective function to optimize, such as:-- which product/service mix to select so as to maximize profit contribution (product mix problem)
-- which product blend to select so as to minimize production cost (blending problem)
-- which supply chain locations to select for a distribution system so as to minimize product throughput time and cost (transportation problem)
-- which airline pilots to tap so as to minimize labor costs (scheduling problem)
-- which capital budget projects to select so as to maximize net present value (capital budgeting problem)
-- which stocks to place in a portfolio so as to maximize return (portfolio selection problem)- "subject to" constraints:
-- labor, machine time, inventory, supplier (for the product mix problem)
-- hops, barley and malt recipe (for a blending problem - at Coors Brewery for example)
-- facility capacity (for the transportation problem)
-- pilot availability and passenger/route demand (for the scheduling problem)
-- project relationships and available capital (for the capital budgeting problem)
-- investment funds available and risk tolerance (for the portfolio problem)
and linear programming problems all have the following mathematical characteristics:
- Decision alternatives are expressed as decision variables
- A single linear objective function to maximize or minimize
- Linear constraints that set upper limits on resources or lower bounds on requirements
- Nonnegative real values (including fractions) for the decision variables
The last three characteristics can be thought of as assumptions, since we have to assume that real world problems can be modeled as single objective problems, with linear objective and constraint equations, and fractions allowed as values for the decision variables. More on these assumptions as we get into extensions to linear programming to address these issues.
Problem Formulation
We begin solving linear programming problems with the problem.
Let's start with a classic product mix problem - one of the earliest
applications of linear programming.
A company plans to make 3 models (A, B, and C) of their main product
next month. Production capacity is limited to 100 total - each model
takes the same about of production time. There is enough cycle stock
inventory to make 200 models, except for the signature finishing
paint. A supplier problem results in only 1,000 gallons being
available next month. Each Model A requires 5 gallons of paint, each
Model B requires 7 gallons and each Model C requires 10 gallons.
Marketing wants the following mix: exactly 20 Model A's; at least 5
Model B's; and no more than 2 Model C's for every Model B produced.
The firm wants to select that product mix so as to maximize profit
contribution. Here are the numbers that go into profit
contribution:
Table 6.1.1
To formulate the linear programming problem means to translate the
word problem statement into mathematical equations called the
objective function and constraint set. The first step in the
formulation is to name the decision variables and their units of
measurement unless the units of measurement are obvious.
The decision variables for this problem are:
A = the number of units of Model A to produce next month
B = the number of units of Model B to produce next month
C = the number of units of Model C to produce next month
The second step is to formulate the objective
function. Here, management must be very careful to precisely
articulate what is to be optimized. In Table 6.1.1, we
see that we could decide a production schedule (how many A's, B's and
C's to produce) so as to minimize costs. Alternatively,
we could decide a production schedule so as to maximize
revenue. Finally, we have sufficient data that we could
decide a production schedule to maximize profit contribution =
revenue - cost. Generally, when variable costs and revenues
are known, the firm would like to determine that production schedule
which maximizes profit contribution, so as not to sub-optimize with a
production schedule.
The objective function to maximize profit contribution is
written:
Maximize Z = (16,000 - 12,000)A + (18,200 - 13,000)B+ (20,000 - 17,000)CMaximize Z = 4,000 A + 5,200 B + 3,000 C
Z is the commonly selected symbol to represent
the value of the objective function, in this case, profit
contribution. We add the word "maximize" or "minimize" to keep our
focus on the appropriate objective. Note first that there is only one
objective. Second, this is a linear algebraic equation with each
decision variable raised to the first power (no squared terms, for
example). Third, the equation represents the additive
property (no cross-products of the decision variables like
B*C, no fractions involving the decision variables such as B/C or 1/B
- only addition and subtraction are allowed in the equation).
If this was the end of the formulation, what should the manufacturer
do? That's right, build an infinite number of Model B's since Model
B's have the highest profit contribution. But, we know there are at
least resource constraints that restrict infinite profit
contribution. For example, we know that production capacity is
limited to 100 total units. What if the firm decided to build all
Model B's - then they would build 100 Model B's. The profit
contribution would be:
Z = 4,000 *(0) + 5,200 * (100) + 3,000 * (0) = $ 520,000
That would be a great profit contribution but
it would be an infeasible solution since we know that
marketing wants to get a broader product line out next month (e.g.,
exactly 20 Model A's). The power of linear programming is that we can
optimize the objective function while mathematically considering
all of the organizational constraints. Let's now
formulate the constraint set.
The first constraint is production capacity being limited to 100
total units. this constraint is written:
A + B + C < 100
This linear equation says all of the A's, plus
all of the B's, plus all of the C's that are produced must be less
than or equal to 100. Note that I made this constraint an
inequality rather than a strict equality.
When there is a choice, it is better to allow slack
in a constraint as this provides maximum flexibility for
other constraints. If 5 A's are built, 5 B's and 5 C's, then 15 total
units are produced. There is slack of 85 units, or
there are 85 units of unused production capacity. If 5 A's, 20 B's
and 75 C's are built, then 100 total units are produced, and there is
no slack. In this case, we say the constraint is
binding on the solution - the firm can't make any more
profit unless it gets some more production capacity.
Another note to make is that all of the decision variables are on the
left hand side of the equation, and the constant is on the right hand
side. This is standard linear programming convention, and this is how
the equation will be entered into The Management Scientist.
The next constraint in the word problem concerns a general inventory
constraint:
A + B + C < 200
Note that this constraint will have slack as
long as the production capacity constraint limits the production to
100 units. Thus, you might suggest leaving out this constraint. There
is nothing wrong with that, except in really big production problems
(e.g. 10 decision variables, 50 constraints), it is very difficult to
keep track of cross-constraint relationships - it is easier to leave
all of the constraints in and let the software identify the binding
and non-binding constraints, including those that are
redundant.
Next comes the paint constraint:
5 A + 7 B + 10 C < 1,000
This constraint shows coefficients other than
an implied "1" in front of the decision variables as in the first two
constraints. These coefficients are called technological
coefficients which represent the rate of usage of the limited
resource. For example, if the firm makes 1 Model A, then 5 gallons of
paint are taken from the 1,000 available. If 2 Model A's are built,
then 10 gallons are taken from the 1,000 available.
Another important note at this point is that this constraint has
units of measurement in gallons, whereas the first two constraints
had units of measurement in units of production. Units of measurement
can be different across the constraints, but must be
the same within a constraint. That is, the left hand
side of the equation units of measurement must be the same as the
right hand side units of measurement. In this case, note that the
right hand side units of measurement are 1,000 gallons.
The left hand side units of measurement are also gallons
since units cancel out in the following coefficient
expressions:
5 gallons / unit * A units = 5 A gallons
I don't want to make this seem complicated - it
will come natural to you when you write constraint equations.
The last three constraints concern the marketing product line mix
constraints. First, marketing wants exactly 20 units of Model A to be
built. That is a strict equality because of the
exactly:
A = 20
Next, marketing wants at least 5 B's to be built. This inequality is written:
B > 5
If the firm builds 10 units of Model B, then there would be a surplus of 5 units. Finally, we have a ratio and proportion constraint. It is best to right this constraint exactly as the word problem presents the ratio and proportion:
C is to B as 2 is to 1, or in equation form with the "no more than":
C / B < 2 / 1
This constraint is legal mathematically, but is not a proper linear programming constraint because of the fraction C / B. So, multiple both sides of the equation by B, and move the decision variables to the left hand side:
C < 2 B; and
- 2 B + C < 0
Let's summarize the objective function and the constraints:
Maximize Z = 4,000 A + 5,200 B + 3,000 C
Subject to:1) A + B + C < 1002) A + B + C < 200
3) 5 A + 7 B + 10 C < 1,000
4) A = 20
5) B > 5
6) - 2 B + C < 0
That's it except for the implied constraints A
> 0, B > 0 and C > 0 (remember then
non-negativity condition I mentioned earlier). Linear programming
computer software packages like The Management Scientist
automatically include the non-negativity constraints so we don't have
to bother about them when using software to solve these type of
problems.
My favorite part of linear programming is problem formulation -
converting organizational considerations into mathematical
expressions - but then I enjoy trying to organize the mob at the
Publix Deli into a single line to minimize average time in line!
After the problem is formulated, we proceed to its solution.
Problem Solution
We already talked about an infeasible solution - any solution
that doesn't work in one or more of the constraints. For example, if
we select the solution:
A = 20, B = 20 and C = 60
let's look at the numbers:
Z = 4,000 (20) + 5,200 (20) + 3,000 (60) = $364,0001) 20 + 20 + 60 = 100 which is = 100: slack = 0;constraint is binding2) 20 + 20 + 60 = 100 which is < 200: slack = 100
constraint is non binding3) 5 (20) + 7 (20) + 10 (60) = 840 which is < 1,000:
slack = 160; constraint is non binding4) 20 = 20; constraint is binding
5) 20 > 5: surplus = 15
6) - 2 (20) + 60 = 20 which is not < 0, this solution is infeasible. If we built 20 B's, the most we could build of C's would be 40 (no more than 2 C's for every B).
The next, and more interesting class of
solutions are the infinite set of feasible solutions.
We can come up with a feasible solution by inspection since this is a
small problem. Looking at the constraint that was infeasible, let's
simply limit the solution to 40 C's and run the numbers:
A = 20, B = 20 and C = 40Z = 4,000 (20) + 5,200 (20) + 3,000 (40) = $304,000
1) 20 + 20 + 40 = 80 which is < 100: slack = 202) 20 + 20 + 40 = 80 which is < 200: slack = 120
3) 5 (20) + 7 (20) + 10 (40) = 640 which is < 1,000:
slack = 3604) 20 = 20; constraint is binding
5) 20 > 5: surplus = 15
6) - 2 (20) + 40 = 0 which is < 0 (the concept of slack/ surplus would not apply to a ratio and proportion constraint)
Since this solution results in a feasible
solution to each constraint, the solution is feasible. Even for small
problems, there are many feasible solutions. We could try a few more,
always trying to increase profit contribution subject to meeting the
constraints. Fortunately, there are algorithms which quickly
determine the most interesting of these many solution: that solution
which is the optimal feasible solution.
The next section introduces The Management Scientist
Linear Programming Module for solving these types of problems. Before
we look at The Management Scientist Linear Programming Model,
I want to introduce one more example. Both of these will be worked by
the software in Module 6.2 Notes.
A Medical Clinic Resource Allocation Model
A small clinic specializes in general and orthopedic surgery.
Each general surgery performed nets $200 to the clinic, and each
orthopedic surgery performed nets $300. There are two constraints of
interest: surgery and therapy. Surgery is limited to 80 person-hours
per week, and therapy to 120 person-hours per week. Each general
patient needs 2 hours of surgery time and 2 hours of therapy. Each
orthopedic patient needs 4 hours of surgery and 12 hours of therapy.
How many general and orthopedic patients should the clinic schedule
to maximize its net profit?
The decision variables for this problem will be:
General = Number of General Surgery patients to schedule for surgery per week
Orth = Number of Orthopedic patients per week
The linear programming problem formulation is then:
Maximize Z = 200 General + 300 Orth
Subject to:1) Surgery Time: 2 General + 4 Orth < 80
2) Therapy Time: 2 General + 12 Orth < 120
I selected this example as a small example so
that we can easily find the optimal solution, and then be able to
replicate this with the software package. This will help us
understand the The Management Scientist linear programming
output. Note that I abbreviated orthopedic to Orth since the software
only allows 8 characters in the names of the decision variables.
With a two decision variable, two constraint maximization problem,
there are only three possible solutions to evaluate. One solution is
to set Orth = 0 and see as many general patients as possible (the
more patients, the higher the profit). The other solution is to set
General = 0 and see as many orthopedic patients as possible. The
final solution is to see as many of each type of patients as possible
- this solution occurs at the intersection of the two constraints set
at capacity. Let's illustrate.
First, lets try a solution that includes all general patients, and no
orthopedic patients.
Looking at the two constraints, if Orth = 0, then we have enough
surgery time to see 40 general patients, and enough therapy time to
see 60 general patients. So, the most we can see is 40 general
patients when Orth = 0 in order to keep a feasible solution. This
solution has the following result:
Z = 200 (40) + 300 (0) = $8,000
1) 2 (40) + 4 (0) = 80; slack = 0; constraint is binding
2) 2(40) + 12 (0) = 80 which is < 120; slack = 40; not binding
Now let's try a solution that includes only orthopedic patients and no general patients. Looking at the two constraints, if General = 0, then we have enough surgery time to see 20 orthopedic patients, and enough therapy time to see 10 orthopedic patient. So, the most we can see is 10 orthopedic patient when General = 0 in order to keep a feasible solution. This solution has the following result:
Z = 200 (0) + 300 (10) = $3,000
1) 2 (0) + 4 (10) = 40; which is < 80; slack = 40; not binding
2) 2 (0) + 12 (10) = 120; slack = 0; constraint is binding
Now for the combination solution. First, set both constraints at their equality and solve the two equations for two unknowns. Do you remember how to do this? If not, don't worry about it since we will be using the software for problem solution. Here goes:
2 General + 4 Orth = 80
2 General + 12 Orth = 120Subtract the second equation from the first:
- 8 Orth = -40Solve for Orth:
Orth = 40/8 = 5Substitute Orth = 5 in the first (or second) equation and solve for General:
2 General + 4 (5) = 80
2 General = 80- 4 (5)
General = (80 - 20) / 2
General = 30The profit for the solution Orth = 5, General = 30 is:
Z = 200 (30) + 300 (5) = $7,500
Since the objective is to maximize net profit,
the first solution with General = 40 and Orth = 0 is the
optimal solution. Of course, some of the medical staff,
such as the orthopedic surgeons may not be happy since they have no
work with this surgery schedule. But that is not the fault of the
method; it is a fault of the formulation. If the orthopedic surgeons
want some work, they have to build that in to the constraint set,
such as Orth > 10 as an added constraint.
You won't be solving linear programming with such a "brute force"
methodology as above, but with The Management Scientist.
6.2: Computer Solution and
Interpretation
We will work the clinic patient
allocation model first. Here is the problem formulation:
Maximize Z = 200 General + 300 Orth
Subject to:1) 2 General + 4 Orth < 80
2) 2 General + 12 Orth < 120
Using The Management Scientist Software Package
To use The Management Scientist Inventory Module to solve
for linear programming problems, click Windows Start/Programs/The
Management Scientist/The Management Scientist Icon/Continue/Select
Module 1 Linear Programming/OK/File/New and you are ready to load
this example problem.
In the next dialog screen, enter 2 for the Number of Decision
Variables and 2 for the Number of Constraints. Then select
Maximize for the Optimization Type; and then select OK.
The next dialog screen first gives you the option to name the
decision variables. X1 and X2 are the default names. I typed General
over the X1 and Orth over the X2. Enter the objective function
coefficients (200 and 300) right below the respective variable names.
Finally, fill out the constraint matrix - it will look almost like
the problem formulation above. Note that you are given just three
choices for the relationship: <, = and >, The < symbol is
used for < constraints and the > symbol for >
constraints.
Here is the solution.
Printout 6.1.1
LINEAR PROGRAMMING
PROBLEM
MAX 200 General+300 Orth
S.T.
1) 2General+4Orth<80
2) 2General+12Orth<120
OPTIMAL SOLUTION
Objective Function Value = 8000.000
Variable Value Reduced Costs
-------------- --------------- ------------------
General 40.000 0.000
Orth 0.000 100.000
Constraint Slack/Surplus Dual Prices
-------------- --------------- ------------------
1 0.000 100.000
2 40.000 0.000
OBJECTIVE COEFFICIENT RANGES
Variable Lower Limit Current Value Upper Limit
------------ --------------- --------------- ---------------
General 150.000 200.000 No Upper Limit
Orth No Lower Limit 300.000 400.000
RIGHT HAND SIDE RANGES
Constraint Lower Limit Current Value Upper Limit
------------ --------------- --------------- ---------------
1 0.000 80.000 120.000
2 80.000 120.000 No Upper Limit
The Management Scientist output not
only gives us the solution, but a great deal of additional
information about the solution. First, the problem formulation is
provided so you can edit your input. Next comes the Optimal
Solution. The objective function value is stated as $8,000,
which confirms our early work "by hand" in Module 6.1 Notes. Next,
comes the values for the decision variables: General has a value of
40, and Orth has a value of 0 - again confirming our earlier
work.
Note that right after the value of the decision variable is a result
called "Reduced Costs." The reduced costs indicate how much each
objective function coefficient would have to improve before the
corresponding decision variable could assume a positive value. For
this problem, the reduced costs for Orthopedic patients is 100. That
means that the profit contribution for Orthopedic patients would have
to increase 100, or be at least 300 + 100 or 400 before Orthopedic
patients would enter the solution. The common sense explanation is
that Orthopedic patients take up so much therapy time that it is not
profitable so schedule any of them (relative to General patients) at
a profit contribution of $300. The reduced costs for General patients
is zero since General patients already have a positive value in the
solution.
The next set of information concerns the constraint set . The first
constraint shows no slack; the second shows slack of 40 - confirming
our work "by hand" in Module 6.1 Notes. Note we also have some
additional information from the computer output. The information is
called "Dual Prices." The Dual Price for the first constraint, which
binds the solution, is $100. This is a very important
result since it gives us the value of one more unit of
the constraining right hand side. If we could get one more unit of
the binding constraint (that is, get one more hour of Surgery time -
raise it from 80 hours to 81 hours), we would get $100 more in profit
contribution. Note that the dual price for the second constraint,
therapy time, is zero since that constraint is not binding.
The next set of information is the Objective Coefficient Ranges. This
is very valuable sensitivity analysis information. As long as the
clinic keeps the profit contribution for general and orthopedic
patients with the lower and upper limits shown, the current solution
(values of the decision variables) remains the optimal solution. This
means that as long as profit for general patients, which is now $200,
stays at or above $150 and at or below infinity, the optimal solution
remains General = 40 and Orth = 0 (of course, the objective function
value changes when the profit contribution changes within the limits
provided). For Orthopedic patients, as long as the profit
contribution stays at or below $400, the current solution of General
= 40 and Orth = 0 remains the optimal solution. Any change beyond
those limits requires rerunning The Management Scientist.
The final set of information is the sensitivity analysis information
on the constraint equation right hand side constants. As long as the
first constraint (surgery time) stays between 0 and 120 hours, the
dual prices can be interpreted as before. As long as the second
constraint (therapy time) stays between 80 and 120 hours, the dual
prices can be interpreted as before. Any change beyond those limits
requires rerunning the problem with The Management
Scientist.
Now let's look at The Management Scientist output for the
product mix problem that we introduced in Module 6.1 Notes and get
information about the optimal solution. Did you work that out by
"brute force" when you were reading the notes? If you did, you can
check your solution to the optimal solution below which shows that
the firm should build 20 Model A's and 80 Model B's. No Model C's are
in solution because their profit contribution is so low, and because
the marketing department did not require any Model C's (they only
required no more than 2 C's for every B produced).
Again, marketing may want to reexamine the constraint or raise the
price by $2,200 (the reduced cost value below) in order to make C's
more profitable.
Note that when you enter data into the management scientist, you need
to enter a "1" if you have an implied "1" for a coefficient. For
example, in the constraint A + B + C < 100, think of it as
1 A + 1 B + 1 C <
100 to get the
For this solution, we see that the first constraint is binding. If we
could get one more unit of production capacity (make it 101 versus
100), we could raise our profit contribution by 5,200. The
sensitivity analysis gives us the ranges for the profit coefficients
and right hand sides that, as long as we stay within these, the
current interpretations are valid.
Printout 6.2.2
LINEAR PROGRAMMING PROBLEM
MAX 4000A+5200B+3000C
S.T.
1) 1A+1B+1C<100
2) 1A+1B+1C<200
3) 5A+7B+10C<1000
4) 1A=20
5) 1B>5
6) -2A+1C<0
OPTIMAL SOLUTION
Objective Function Value = 496000.000
Variable Value Reduced Costs
-------------- --------------- ------------------
A 20.000 0.000
B 80.000 0.000
C 0.000 2200.000
Constraint Slack/Surplus Dual Prices
-------------- --------------- ------------------
1 0.000 5200.000
2 100.000 0.000
3 340.000 0.000
4 0.000 -1200.000
5 75.000 0.000
6 40.000 0.000
OBJECTIVE COEFFICIENT RANGES
Variable Lower Limit Current Value Upper Limit
------------ --------------- --------------- ---------------
A No Lower Limit 4000.000 No Upper Limit
B 3000.000 5200.000 No Upper Limit
C No Lower Limit 3000.000 5200.000
RIGHT HAND SIDE RANGES
Constraint Lower Limit Current Value Upper Limit
------------ --------------- --------------- ---------------
1 25.000 100.000 148.571
2 100.000 200.000 No Upper Limit
3 660.000 1000.000 No Upper Limit
4 0.000 20.000 95.000
5 No Lower Limit 5.000 80.000
6 -40.000 0.000 No Upper Limit
The last section of this note set shows
some popular applications of linear
programming.
6.3: Applications
Finance Example
Here is a finance example that should help with the case for this
module. Western Trust invests in various types of securities. They
have $5 million for immediate investment and wish to maximize the
interest earned over the next year. Risk is not a factor. four
investment alternatives include Bonds, Stocks, Gold, and Land. The
expected return for Bonds is 6%, Stocks 14%, Gold 10%, and Land 5%.
The maximum amount to be invested for each alternative is $3 million
for Bonds, $3 million for Stocks, $2 million for Gold, and $1 million
for Land. Risk is not a factor (but it is in Case 6!). To structure
the portfolio, the Senior VP has specified at least 40% of the
investment has to be in corporate bonds and common stock; and no more
than 20% of the investment is to be in Land. The objective is to
maximize the return.
The decision variables are:
B = Dollars to invest in Bonds
S = Dollars to invest in Stocks
G = Dollars to invest in Gold
L = Dollars to invest in Land
The objective function is maximize return (this would be in percent units); followed by the constraint set:
Maximize Z = 0.06 B + 0.14 S + 0.10 G + 0.05 L
Subject to:1) B + S + G + L < 5,000,000
2) B < 3,000,000
3) S < 3,000,000
4) G < 2, 000,000
5) L < 1,000,000
6) B + S > 0.40 (B + S + G + L), which givesB + S > 0.4 B + 0.4 S + 0.4 G + 0.4 L, which gives
(1 - 0.4) B + (1 - 0.4 ) S - 0.4 G - 0.4 L > 0, which gives
0.6 B + 0.6 S - 0.4 G - 0.4 L > 0
7) L < 0.2(B + S + G + L), which givesL < 0.2 B + 0.2 S + 0.2 G + 0.2 L, which gives
- 0.2 B - 0.2 S - 0.2 G + 0.8 L < 0
A couple of comments are in order. Note that I made constraint number
one a < constraint. You could argue that it should be a
strict equality, but this gives us a general formulation that, along
with the way I modeled constraints 6 and 7, only require changing the
$5 million right hand side in constraint 1 if next month a different
amount is available. Also note that constraints 2 through 5 are
< constraints, and they have to be or the problem becomes
infeasible. Finally, note that constraints 6 and 7 are in general
form, which is usually preferred. That is, you could interpret 40% of
the investment to be $2 million (40% of $5 million). However, the
general way to write the total investment is B + G + S + L and this
way gives more modeling flexibility.
You should be ready to tackle Case Number 6. Drafts for my "free
review" of Case 6 are due March 28th.
Here is the linear programming printout solution
for the above finance application
Printout 6.3.1
LINEAR PROGRAMMING PROBLEM
MAX 0.06B+0.14S+0.1G+0.05L
S.T.
1) 1B+1S+1G+1L<5000000
2) 1B<3000000
3) 1S<3000000
4) 1G<2000000
5) 1L<1000000
6) .6B+.6S-.4G-.4L>0
7) -.2B-.2S-.2G+.8L<0
OPTIMAL SOLUTION
Objective Function Value = 620000.000
Variable Value Reduced Costs
-------------- --------------- ------------------
B 0.000 0.040
S 3000000.000 0.000
G 2000000.000 0.000
L 0.000 0.050
Constraint Slack/Surplus Dual Prices
-------------- --------------- ------------------
1 0.000 0.100
2 3000000.000 0.000
3 0.000 0.040
4 0.000 0.000
5 1000000.000 0.000
6 1000000.000 0.000
7 1000000.000 0.000
OBJECTIVE COEFFICIENT RANGES
Variable Lower Limit Current Value Upper Limit
------------ --------------- --------------- ---------------
B No Lower Limit 0.060 0.100
S 0.100 0.140 No Upper Limit
G 0.060 0.100 0.140
L No Lower Limit 0.050 0.100
RIGHT HAND SIDE RANGES
Constraint Lower Limit Current Value Upper Limit
------------ --------------- --------------- ---------------
1 3000000.000 5000000.000 5000000.000
2 0.000 3000000.000 No Upper Limit
3 3000000.000 3000000.000 5000000.000
4 2000000.000 2000000.000 No Upper Limit
5 0.000 1000000.000 No Upper Limit
6 No Lower Limit 0.000 1000000.000
7 -1000000.000 0.000 No Upper Limit
on Duty
The optimal solution calls for $3 million in
Stocks and $2 million in Gold, for a return of $620,000 in interest,
or an average of 620,000/5,000,000 = 12.4% return. The solution
information for the decision variables includes reduced costs for B
of 0.04. Recall this is the amount the objective function coefficient
for B would have to improve before B could assume a positive value
(come into the solution). Currently, the return on bonds is 6% - that
would have to go to 10% before Bonds enter the solution relative to
the variables in solution. So if there is a desire to add bonds to
the solution, we would have to add a constraint forcing bonds in
since their return will not go much above 6% in today's market. The
reduced costs for land are is interpreted the same way.
The constraint output information includes dual prices. For example,
the dual price for the third constraint is 0.04. This means that if
the 3 million limit on stocks could be raised to 3,000,001, the
objective function would increase by 0.04, or there would be a return
of 4% on that additional dollar. Side note: if the 3 million limit
were reduced by 1, the objective function would
decrease 0.04. Also note the fifth constraint shows no
reduced cost - that is because there is slack of $1,000,000 in this
constraint so we would not want to raise the upper bound from
1,000,000 to 1,000,001 since we aren't investing in land in this
optimal solution.
The objective function ranges give us the sensitivity analysis for
the objective function coefficients. For example, the current
solution of S = 3,000,000 and G = 2,000,000 remains the optimal
solution as long as B' s return remains below 0.10; S's return
remains above 0.10, G remains between 0.06 and 0.14, and L below
0.10. This is really powerful sensitivity analysis information for
Western Trust.
The right hand side ranges give us the sensitivity analysis for the
constraint equations. Essentially, as long as the right hand side
values remain within the lower and upper limits shown, the dual
prices are constant and may be interpreted. Thus, as long as the
amount to invest in the third constraint is between 3 million and 5
million, the dual price remains at 0.04.
Scheduling Example
Let's look at a simple scheduling problem (Problem 8, p. 379) -
the Clark County Sheriff's Department. The department schedules
police officers for six 8-hour shifts starting at 8 a.m., noon, 4
p.m., 8 p.m., midnight, and 4 a.m. The demand for officers varies
depending on the time of day. Data analysis reflects the
following:
Table 6.3.1
The objective is to schedule officers so as to minimize cost, that
is, to minimize the number of officers on each shift. The problem is
that officers work 8 hour shifts, yet the demand comes in 4 hour
chunks. That is the service system scheduling dilemma, and that is
why agencies such as banks have gone to flex time for tellers.
Minimization problems are handled just like maximization problems,
except for the interpretation of the dual costs, which I will address
a little bit later.
To formulate this problem, let's begin with the decision
variables:
Shift1 = Number of officers scheduled to come in on Shift 1
Shift2 = Number of officers scheduled to come in on Shift 2
Shift3 = Number of officers scheduled to come in on Shift 3
Shift4 = Number of officers scheduled to come in on Shift 4
Shift5 = Number of officers scheduled to come in on Shift 5
Shift6 = Number of officers scheduled to come in on Shift 6
We want to minimize the total number of officers scheduled, so:
Minimize Z = Shift1 + Shift2 + Shift3 + Shift4 + Shift5 + Shift6
Now the constraints are used to ensure we have
time of day coverage. We have to ensure that 5 officers provide
coverage between 8 am and noon. We get this coverage from Shift1,
whose officers come in at 8 am, but also from Shift6, whose officers
come in at 4 am and work until noon. Proceeding with this logic, here
are the constraint equations:
Subject to:Shift6 + Shift1 > 5
Shift1 + Shift2 > 6
Shift2 + Shift3 > 10
Shift3 + Shift4 > 7
Shift4 + Shift5 > 4
Shift5 + Shift6 > 6
Can you come up with the optimal solution while
I go off to run The Management Scientist solution?
(five minute pause)
....... I'm back. Did you figure that the department needs a minimum
of 19 officers to meet the shift demand schedule, with 3 officers
needed on Shift1, 3 on Shift2, 7 on Shift3, none on Shift4, 4 on
Shift5 and 2 on Shift6? The computer solution in Printout 6.3.2 also
shows negative 1's for the dual prices. Negative values for dual
costs in minimization problem constraints means the objective
function will "worsen" or get bigger when the right hand side of that
constraint increases. For example, in constraint 2 if the right hand
side of 10 were increased to 11, the objective function would worsen
by 1, or we would need 20 officers instead of 19.
Printout 6.3.2
LINEAR PROGRAMMING
PROBLEM
MIN 1Shift1+1Shift2+1Shift3+1Shift4+1Shift5+1Shift6
S.T.
1) 1Shift1+1Shift2>6
2) 1Shift2+1Shift3>10
3) 1Shift3+1Shift4>7
4) 1Shift4+1Shift5>4
5) 1Shift5+1Shift6>6
6) 1Shift1+1Shift6>5
OPTIMAL SOLUTION
Objective Function Value = 19.000
Variable Value Reduced Costs
-------------- --------------- ------------------
Shift1 3.000 0.000
Shift2 3.000 0.000
Shift3 7.000 0.000
Shift4 0.000 0.000
Shift5 4.000 0.000
Shift6 2.000 0.000
Constraint Slack/Surplus Dual Prices
-------------- --------------- ------------------
1 0.000 0.000
2 0.000 -1.000
3 0.000 0.000
4 0.000 -1.000
5 0.000 0.000
6 0.000 -1.000
OBJECTIVE COEFFICIENT RANGES
Variable Lower Limit Current Value Upper Limit
------------ --------------- --------------- ---------------
Shift1 0.000 1.000 1.000
Shift2 1.000 1.000 2.000
Shift3 1.000 1.000 1.000
Shift4 1.000 1.000 No Upper Limit
Shift5 0.000 1.000 1.000
Shift6 1.000 1.000 2.000
RIGHT HAND SIDE RANGES
Constraint Lower Limit Current Value Upper Limit
------------ --------------- --------------- ---------------
1 3.000 6.000 6.000
2 10.000 10.000 No Upper Limit
3 0.000 7.000 7.000
4 4.000 4.000 6.000
5 4.000 6.000 6.000
6 5.000 5.000 8.000
Period Selling Price Per Unit Regular Production Cost Per Unit Overtime Production Cost per Unit Regular Production Capacity in Units Overtime Production Capacity in Units Ending Inventory Cost Per Unit Demand 1 $5.00 $2.80 $3.36 250 100 $0.50 500 2 $5.00 $2.90 $3.48 300 100 $0.50 300 3 $5.50 $3.00 $3.60 300 125 $0.55 400
Multiperiod Production and Inventory
Planning Model (Case 7)
These models are used to determine a production, inventory and
lost sales schedule so as to minimax cost or maximize profit over a
multiperiod planning horizon. Here is some pertinent information for
Allen Manufacturing Company (Problem 23, pp. 385-386 in the text).
Table 6.3.2.
Other pertinent planning information includes the lost sales cost of
$4 per unit in any period. This amount accounts for the loss of
customer good will, but does not include lost revenue which may also
apply. The beginning inventory for period 1 is 100 units, and the
firm would like to have at least 50 units in ending inventory for
period 3 to prepare for period 4.
The objective for this planning model is to determine the sales,
regular time production amount, overtime production amount, ending
inventory and lost sales for each of the production periods.
We begin the formulation by identifying the many decision variables
needed to answer the above objective. Each decision variable is
measured in units (e.g., amount of sales in units).
S1 = Sales (in units) in period 1
S2 = Sales (in units) in period 2
S3 = Sales (in units) in period 3
RP1 = Regular production (in units) in period 1
RP2 = Regular production (in units) in period 2
RP3 = Regular production (in units) in period 3
OP1 = Overtime production (in units) in period 1
OP2 = Overtime production (in units) in period 2
OP3 = Overtime production (in units) in period 3
BI = Beginning Inventory (in units)
EI1 = Ending inventory (in units) in period 1
EI2 = Ending inventory (in units) in period 2
EI3 = Ending inventory (in units) in period 3
LS1 = Lost sales (in units) in period 1
LS2 = Lost sales (in units) in period 2
LS3 = Lost sales (in units) in period 3
We need a few more variables to complete model this production
planning problem, although the variables are not decision variables
and only appear in constraints. These include a variable for
beginning inventory and three variables for demand:
BI = Beginning Inventory (in units)
D1 = Demand in period 1 (in units)
D2 = Demand in period 2 (in units)
D3 = Demand in period 3 (in units)
The objective is to maximize profit, which is sales revenue minus
costs (regular production, overtime production, inventory, and lost
sales) for each of the three periods:
Maximize Z = 5.00S1 - 2.80RP1 - 3.36OP1 - 0.50EI1 - 4.00LS1+ 5.00S2 - 2.90RP2 - 3.48OP2 - 0.50EI2 - 4.00LS2+ 5.50S3 - 3.00RP3 - 3.60OP3 - 0.55EI3 - 4.00LS3
For the constraints, let's start with meeting customer demand in each of the three period. Note that every production or service planning model will have customer demand as something that has to be met. The objective is still maximize profit but the demand has to be met in the long run or the firm doesn't survive. This may be a good time to note also that we need three separate constraints in this model, since D1+D2+D3 = 1200 may result in not meeting each period's demand. That is, if D1 = D2 = 0 and D3 = 1200 would be feasible to D1+D2+D3 =1200, but not to this problem. Also note that I made demand constraints as strict equalities. That is possible in this problem since inventory can handle excess demand, and lost sales shortages in demand.
1) Demand in period 1: D1 = 500
2) Demand in period 2: D2 = 300
3) Demand in period 3: D3 = 400
Every production or service planning model generally also have capacity constraints. In this case, we have both regular and overtime production capacity constraints.
4) Regular in period 1: RP1 < 250
5) Regular in period 2: RP2 < 300
6) Regular in period 3: RP3 < 300
7) Overtime in period 1: OP1 < 100
8) Overtime in period 2: OP2 < 100
9) Regular in period 3: OP3 < 125
Production planning problems need to include inventory constraints, unless inventory is not part of the picture (for example, companies that make perishable products may not have inventory constraints). Service companies obviously do not have inventory constraints. The beginning inventory is 100 units left over from last production cycle: that will be a strict equality. There is no requirement to have ending inventory from period 1 to 2, or from period 2 to 3. However, the firm stipulated that at the end of this three-period production cycle, it needs to have at least 50 units to go forward to the next cycle. The constraints are:
10) Beginning Inventory: BE = 100
11) Ending Inventory: EI3 > 50
Production planning models often include balance constraints that
incorporate or model what happens when we produce more
than we sell in periods 1, 2 and 3. When we produce more than we
sell, we create ending inventory for the following period. Ending
inventory results from starting with beginning inventory from the
previous period, adding regular and overtime production, and
subtracting sales.
12) Ending inventory in period 1: EI1 = BE + RP1 + OP1 - S1
13) Ending inventory in period 2: EI2 = EI1 + RP2 + OP2 - S2
14) Ending inventory in period 3: EI3 = EI2 + RP3 + OP3 - S3
We also need a set of constraints to model the situation that occurs
when we produce less than we could have sold in periods
1, 2 and 3. When we produce less than we could have sold, we generate
lost sales.
15) Lost Sales in period 1: LS1 = D1 - S1
16) Lost Sales in period 2: LS2 = D2 - S2
17) Lost Sales in period 3: LS3 = D3 - S3
Of course, all of the constraints have to be
rewritten to put them in standard form for the linear program data
input. That is shown in the computer input and output below. The
computer output provides the solution values for the production
planning decision and input variables, as well as rich sensitivity
analysis information.
Printout 6.3.3
LINEAR PROGRAMMING PROBLEM
MAX 5S1+5S2+5.5S3-2.8RP1-2.9RP2-3RP3-3.36OP1-3.48OP2-3.6OP3-0.5EI1-0.5EI2-0.55EI
3-4LS1-4LS2-4LS3
S.T.
1) 1D1=500
2) 1D2=300
3) 1D3=400
4) 1RP1<250
5) 1RP2<300
6) 1RP3<300
7) 1OP1<100
8) 1OP2<100
9) 1OP3<125
10) 1BE=100
11) 1EI3>50
12) 1S1-1RP1-1OP1+1EI1-1BE=0
13) 1S2-1RP2-1OP2-1EI1+1EI2=0
14) 1S3-1RP3-1OP3-1EI2+1EI3=0
15) 1S1+1LS1-1D1=0
16) 1S2+1LS2-1D2=0
17) 1S3+1LS3-1D3=0
OPTIMAL SOLUTION
Objective Function Value = 2367.000
Variable Value Reduced Costs
-------------- --------------- ------------------
S1 450.000 0.000
S2 300.000 0.000
S3 400.000 0.000
RP1 250.000 0.000
RP2 300.000 0.000
RP3 300.000 0.000
OP1 100.000 0.000
OP2 25.000 0.000
OP3 125.000 0.000
EI1 0.000 6.020
EI2 25.000 0.000
EI3 50.000 0.000
LS1 50.000 0.000
LS2 0.000 5.520
LS3 0.000 5.520
BE 100.000 0.000
D1 500.000 0.000
D2 300.000 0.000
D3 400.000 0.000
Constraint Slack/Surplus Dual Prices
-------------- --------------- ------------------
1 0.000 -4.000
2 0.000 1.520
3 0.000 1.520
4 0.000 6.200
5 0.000 0.580
6 0.000 0.980
7 0.000 5.640
8 75.000 0.000
9 0.000 0.380
10 0.000 9.000
11 0.000 -4.530
12 0.000 9.000
13 0.000 3.480
14 0.000 3.980
15 0.000 -4.000
16 0.000 1.520
17 0.000 1.520
OBJECTIVE COEFFICIENT RANGES
Variable Lower Limit Current Value Upper Limit
------------ --------------- --------------- ---------------
S1 -0.640 5.000 No Upper Limit
S2 -0.520 5.000 No Upper Limit
S3 -0.020 5.500 No Upper Limit
RP1 -9.000 -2.800 No Upper Limit
RP2 -3.480 -2.900 No Upper Limit
RP3 -3.980 -3.000 No Upper Limit
OP1 -9.000 -3.360 No Upper Limit
OP2 -9.000 -3.480 -3.100
OP3 -3.980 -3.600 No Upper Limit
EI1 No Lower Limit -0.500 5.520
EI2 -6.020 -0.500 -0.120
EI3 No Lower Limit -0.550 3.980
LS1 No Lower Limit -4.000 1.640
LS2 No Lower Limit -4.000 1.520
LS3 No Lower Limit -4.000 1.520
BE No Lower Limit 0.000 No Upper Limit
D1 No Lower Limit 0.000 No Upper Limit
D2 No Lower Limit 0.000 No Upper Limit
D3 No Lower Limit 0.000 No Upper Limit
RIGHT HAND SIDE RANGES
Constraint Lower Limit Current Value Upper Limit
------------ --------------- --------------- ---------------
1 450.000 500.000 No Upper Limit
2 275.000 300.000 375.000
3 375.000 400.000 475.000
4 0.000 250.000 300.000
5 225.000 300.000 325.000
6 225.000 300.000 325.000
7 0.000 100.000 150.000
8 25.000 100.000 No Upper Limit
9 50.000 125.000 150.000
10 0.000 100.000 150.000
11 25.000 50.000 125.000
12 -450.000 0.000 50.000
13 -75.000 0.000 25.000
14 -75.000 0.000 25.000
15 -50.000 0.000 No Upper Limit
16 -25.000 0.000 75.000
17 -25.000 0.000 75.000
By now we have worked a product mix
problem, a clinic patient mix problem, a couple of financial planning
problems, a scheduling problem and a production planning problem. I
do hope you are beginning to appreciate the wide range of
applications for linear programming. In the next two modules we
examine some additional extensions.
|
|
|